ERCOT Targets a Dec. 10 Report on Data Center Grid Impacts; Oncor Lists a Large Queue

A preliminary Nov. 5 presentation to state utility regulators, and Oncor's third-quarter results the same day, describe a large wave of data-center interconnection requests. Those figures are requests, not a list of projects approved in Princeton.

The Electric Reliability Council of Texas told the Public Utility Commission of Texas on Nov. 5, 2026, that it is targeting a final public report on Dec. 10 on the state and community impacts of data center interconnection requests. The Nov. 5 presentation is labeled a preliminary summary and subject to change.

ERCOT said it issued a request for information to 465 loads and that 433, or 93%, responded, covering about 177 gigawatts, or about 97%, of requested capacity. All 245 large loads — projects of 75 megawatts or greater — responded, representing about 166 gigawatts. Requests span every ERCOT load zone, the presentation says, with West Texas the plurality at 41% of capacity, or 73 gigawatts, and the North Load Zone at about 45 gigawatts.

The same day, Oncor Electric Delivery said in its third-quarter 2026 results that as of Sept. 30 its active transmission large commercial and industrial queue included 795 requests. Those included about 293 gigawatts from data centers and about 19 gigawatts from other industrial sectors, including 4 gigawatts of crypto-mining facilities. Those are queue requests, not projects already built.

Oncor also said ERCOT had given conditional Batch Zero classifications of about 24 gigawatts of large load as base load, including 10 gigawatts already energized, and 21 gigawatts as studied load where Oncor is the transmission provider. The company said that is pending an ERCOT audit expected in December 2026, with a final transmission plan not expected until fall 2027.

Why it matters in Princeton

Princeton is in the ERCOT power region. The preliminary summary assigned about 45 gigawatts of requested capacity to the North Load Zone, a large North Texas zone. Neither document lists a project in Princeton. The fuller public report is targeted for Dec. 10.

Sources: ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUC Open Meeting, Nov. 5, 2026 Oncor reports third quarter 2026 results, Nov. 5, 2026